Archer House, Britland industrial estate

The original Asphalt roof of Archer House was failing and water ingress was being reported in the busy accountancy offices below. It was decided that the roof would benefit from a warm roof felt overlay.

The existing asphalt was prepared suitably and a new VCL layer was applied, before installing new 150mm insulation to upgrade the office buildings thermal efficiency. A Danosa 20 year felt system was then installed to the area and the high parapets encapsulated, before installing an aluminium trim. New PV solar panels were then installed.

After

Archer House
Archer House
Archer House

Project Details

Client: Brighton & Hove City Council
Location: Hove, UK
 1000m2 Flat Roof Area
 Works completed within 8 weeks

System Details

StressPly Self-Adhesive Metal Lined VCL
Tapered Insulation Scheme
 Garland TorchFlex Ultravent Underlay to area
 Garland TorchFlex Base Sheet to details
 Garland StressPly cap sheet in Red